Skip to main content

Entergy Transmission Towers

Location: Luna, AR & Greensville, MS
Owner: Entergy Arkansas, Inc.
Specialty Contractor: STRUCTURAL

Entergy Arkansas repaired and strengthened cracked concrete foundations at two transmission towers by monitoring and testing the damage, injecting epoxy into cracks, and reinforcing the columns with carbon FRP systems, successfully extending the towers’ service life despite challenging site and weather conditions.

FRP installation and excavation backfilling around the support bases on all 4 tower legs are complete.
Epoxy injection was performed using “port-to-port” technique.
Epoxy injection completed. Surface seal and injection ports were removed using diamond cup grinders.
Pressure epoxy injection of cracks
Existing cracks in the column foundation were repaired using epoxy injection.
The isolated square-shaped foundations for each tower, are 14’-0” x 14’-0” and 3’-0” deep. The top of the foundation is 3’-0” below grade, each of the foundations are connected together with 3’-0” x 2’-6” tie beams and consists of nine (9) 18” diameter.
Both transmission towers in need of repair and strengthening are located along the Mississippi River.
The concrete columns were designed in the shape of a frustum pyramid with square sections at top and bottom (4’-0” at the top and about 9’-0” at the bottom).
The cracks ranged from 0.003” to 0.5” in with several cracks running from the top anchor connections and steel framing down to the base of the tower leg.
FRP layout for concrete supports in Tower 107A
Section enlargement at base of support
Elevation of Concrete Support Enlargement – Tower 106A

PROJECT DETAILS

Entergy Arkansas, Inc., located in New Orleans, serves approximately 705,000 residential and commercial customers with electric services in the Mississippi-Arkansas region. During routine inspections of their transmission towers, several cracks were discovered in the concrete foundations of tower 106A in Luna, Arkansas and in the foundations of tower 107A in Greensville, Mississippi.

Repairing Cracks & Strengthening Foundations

The towers were surveyed and monitored to track any movement or width changes in the cracking for several months. Additional concrete material testing, including petrographic analysis for Alkaiai-Silica Reaction (ASR) and Uranyl Acetate Reagent solution testing was also conducted. The structural evaluation report revealed that although the existing structure components had adequate strength to support the towers’ design loads, the discovered cracks were moving and propagating, and the effects of the external loads had also weakened the columns. It was determined that the best, and most cost-effective, solution was to repair the cracks by injecting them with epoxy, then strengthen the tower column supports using Tstrata’ V-Wrap™ C400H high-strength carbon fiber fabric and its V-Wrap™ Carbon FRP Rod.

Overcoming Challenges

Crews faced several challenges during the repair process and the installation of the FRP system, including extreme weather temperatures, high winds and heavy rains. These weather conditions also made travel and access to each tower and material and equipment storage near the towers difficult, requiring the use of all-terrain vehicles and crews to perform the work mostly on scaffolding.

Ultimately, this project was successfully completed to the owner’s satisfaction and within budget. Together, the contracting expertise of STRUCTURAL and the product and design solutions provided via Tstrata resolved the cracking and weakening in the transmission towers’ concrete foundations, increasing the life span of both structures.

highlights

Significant cracking was found in the concrete foundations of two transmission towers along the Mississippi River.
The cracks were repaired with epoxy injections.
Strengthening solutions included the installation of Tstrata’ V-Wrap™ C400H high strength carbon fiber fabric and its V-Wrap™ Carbon FRP Rod.